Paid Rs 2.06 cr, got no flat; Court rejects builder’s delay argument, orders interest
Times of India
October 19, 2026
via Times of IndiaYou're reading one story from Newsaly
Newsaly brings together 60,000+ newspaper articles, 30,000+ podcasts and 10,000+ magazine articles from around the world.
A World Of News, One Window.
Explore Today's NewsTwo homebuyers filed a case against the builder. The dispute concerned an apartment for which they had signed the sale agreement in 2014, with possession due by June 30, 2017. The flat's consideration was Rs 1.95 crore. By the time of the complaint, the buyers had paid Rs 2.06 crore, including the c